Showing this would be available as a result of refurbishment, for the same duty head
Noting this exceeded the OEM performance
Showing tests to be a vital tool in confirming post-refurbishment capability
We we were approached to test two 8MW boiler feed pumps at the client’s 1000MW coal-fired power station in Southern Australia.
Utilising our FREEFLOW portable system, we were tasked with completing on-site tests on the pumps, as the client wanted to confirm that they were performing the same as, or better than, the OEM’s as-new condition. Our client was keen to identify further remedial works and explore other system optimisation opportunities.
Our fuller case study offers in-depth analysis of this project. It details the challenges faced, our approach and the solutions we implemented, as well as results achieved. You can request a copy by completing the form below.